We have been awarded additional scope of services by CPECC for providing Flange management services to ongoing bab Integrated Facilities project.The project is been awarded to CPECC from ADNOC Onshore for the Engineering, procurement, and Construction of BIFP project in Abu Dhabi UAE. Our in house developed service is ccapable of carrying out the complete flange manage,ent system using Barcode & Mobile application interface.
In this project , we shall set up database for the flanges based on sub-system marked-up P&ID drawings and marked up on the P&ID drawings with unique flange number for each individual flange based on sub-system number, line number, isometric number as defined by the client.
Petrofac was awarded a contract in 2019 worth around US$1 billion with Groupment Isarene, the joint operating group set up by Sonatrach and Petroceltic, for the Ain Tsila Development Project in Algeria. We have secured the scope of implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site.
The project is Located around 1,100 kilometres south-east of Algiers, the Ain Tsila field will produce gas, LPG and Condensate, for the local Algerian market and for export. Under the terms of the 42-month contract, the lump-sum engineering, procurement and construction (EPC) project scope of work includes commissioning, start-up and performance testing.
APM Thai has secured a new multimillion project from Petrofac, Samsung, Saipem JV for the implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site. The project also includes the scope of providing RFID solutions for finished spool movement control.
Petrofac, leading a consortium with Saipem S.p.A. (Saipem) and Samsung Engineering Co Ltd (Samsung), has awarded the contract from Thai Oil Public Company Limited’s Clean Fuels Project on the East coast of Thailand. The scope of work encompasses engineering, procurement, construction and commissioning services. The contract includes improvements and expansion at the existing facility as well as the addition of new complex processing units, all required utilities and supporting facilities.
We are pleased to announce the opening of our new office in Samut Prakan. Thailand to cater professional services to our projects globally. The new office will function as Amogh projects Thai Co.Ltd.
APM secured a new project from Petrofac International LLC for the the implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site.
Petrofac was awarded the engineering, procurement and construction (EPC) contract from Sonatrach for EPC1 of the Tinrhert Field Development Project in Algeria. Located in Ohanet, around 1,500 kilometres southeast of Algiers, EPC1 will provide a new inlet separation and compression centre. Under the terms of the 36-month contract, the scope of work includes a pipeline network of approximately 400 km to connect 36 wells, along with commissioning, start-up and performance testing of facilities.
Petrofac, in a 50/50 joint venture with Samsung Engineering, was awarded the EPC package 2 contract from Duqm Refinery and Petrochemicals Industries Company LLC. The scope of work includes the engineering, procurement, construction, commissioning, training and start-up operations for all the utilities and offsites at Duqm.
We have been awarded the whole scope which includes the implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site. The project also includes the scope of providing barcode & similar pipe/material tracking solutions.
APM has associated with reputed client, China Petroelum Eningeering & Construction Corporation (CPECC) and secured the pilot project, for the execution of Piping & Spool management software including material traceability. CPECC entered into the contract with ADNOC Onshore (Abu Dhabi Company for Onshore Oil Operations) for the engineering, Procurement and construction of BAB Integrated Faciliites Project.(BIFP) Our scope of services include to carry out the performance of Piping & Spool management software service.
Further similar project as BPCL was awarded to VAPM from Petrofac for Vedanta Limited for its Raageshwari Deep Gas Field Development Project located in Barmer, Rajasthan, India. The scope includes the implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site.
VAPM secured a new project from Petrofac who has been awarded a lump-sum Engineering, Procurement and Construction (EPC) contract by Bharat Petroleum Corporation Limited (BPCL). The scope includes the implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site.
We are pleased to announce the opening of our new office in Vizag, India to cater professional services to our projects globally. The new office will function as Vizag Amogh Management Pvt Ltd.
APM secured its new project with Petrofac International LLC for providing Integrated Piping Management system for the execution of Turkstream receiving terminal project, Turkey. Petrofac has been awarded EPC contract with South Stream Transport B.V., a wholly owned subsidiary of GAZPROM, for the development of onshore pipelines and a gas receiving terminal near Kıyıköy in Turkey. When completed, the facility will receive 31.5 billion cubic metres of gas annually from the Turkstream pipeline originating from the compressor station in Anapa, Russia.
APM has been successfully awarded a new project from Petrofac International Limited for providing Integrated Piping Management system for the execution of GC 32 New gathering Centre for SEK, Kuwait. Petrofac has been awarded the contract from Kuwait Oil Company’s (KOC) gathering centre project, GC 32, located in the Burgan oil field, south east of Kuwait.The lump-sum engineering, procurement and construction (EPC) project, is the first sour gathering centre to be developed in the field and will process crude oil and associated gas recovered from the Arifjan, Marat, Minagish Oolite and Burgan Wara high Hydrogen Sulphide fields.
Our scope includes the implementation and configuration of IPMS system for providing professional services which includes management of spool drawing, weld data management of spools in shop, piping progress monitoring front forecasting and other necessary support to successfully complete the piping fabrication works & necessary support at Project site.
APMAPM secured our first contract with Petrofac E&C Oman LLC with the award of Material management services for Ghazer Project Khazzan Central Processing Facility, CPF in Oman. The project was awarded to Petrofac by BP Exploration Limited (Epsilon) for the Phase 2 gas development in the Sultanate of Oman. This follows the Phase 1 CPF Khazzan project, awarded to Petrofac in February 2014, which celebrated first gas on 22 September 2017.
The scope of our services includes Material management services by AMOGH including SpoolGen, Progress monitoring, Fabrication & Erection material simulation, Tracking, monitoring, shortage material analysis with ETA etc.